Complete Projects

COMPLETED-PROJECTS

Beneficiaries: 896 No. of Houses: 176 – 5% Completed year: Nov. 2022 Approved Budget: Rs. 82.06 Lacs FACILITIES PROVIDE
  1. Site Survey
  2. Detail Estimate
  3. Base Line Survey
  4. Underground Sewerage System –
  5. Baffled Tanks with Treatment plants –
  6. Pavers in Street
  7. Street Lights
  8. Children Park
Leadership:
  • Mr. Gurchetan Singh Kandola, NRI
  • S. Gurmail Singh, NRI
  • S. Gurdial Singh
  • S. Surinder Singh
  • Mr. Roop Lal
Beneficiaries: 2517
No. of Houses: 643 – 30%
Completed year: Nov. 2022
Approved Budget: Rs. 185.88 Lacs
FACILITIES PROVIDE
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System –
  4. Pavers in Street –
  5. Baffled Tanks with Treatment plants –
  6. Street Lights
Leadership: Mr. Santokh Singh (NRI), S. Dilbag Singh (NRI), S. Avtar Singh (NRI), S. Chur Singh (NRI), S. Lakhvir Singh, S. Girdawar Singh
Beneficiaries: 3416
No. of Houses: 887 – 70%
Completed year: 2016
Approved Budget: Rs. 312.28 Lacs
FACILITIES PROVIDE
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 48000 rft.
  4. Water Supply- 30000 rft.
  5. Pavers in Street – 27000 sqft.
  6. Baffled Tanks with Treatment plants-1
  7. Cremation Ground with Gas system-1
Leadership: Mr. Shiv Singh Jaswal (NRI), Brig. J.S.Jaswal, S. Avtar Singh, S. Resham Singh
Beneficiaries: 561
No. of Houses: 117 – 100%
Completed year: 2012
Money Spent: Rs. 65.00 Lacs
FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 7500 rft.
  4. Water Supply- 4700 rft.
  5. Overhead Water Tank – 1 no.
  6. Paved Streets – 44000 sqft.
  7. Baffled Tank - 1 no.
  8. Street Electric Lights
Leadership: Dr.Amarjit Singh Marwah (NRI), S. Pal Singh
Beneficiaries: 1104 No. of Houses: 179 – 100% Completed year: 2010 Money Spent: Rs. 65.00 Lacs FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 13095 rft.
  4. Water Supply (One part) – 7159 rft.
  5. Concreting of Streets – 63943 sqft.
  6. Baffled Tank - 1 no.
Leadership: Mr. Satpal Multani, Mr. Tarsem Singh
Beneficiaries: 3013
No. of Houses: 515 – 100%
Completed year: 2011
Money Spent: Rs. 154.75 Lacs
FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 41724 rft.
  4. Concreting of Streets – 220000 sqft.
  5. Baffled Tank - 2 nos.
  6. Building – Computer & Library Room
  7. Training:-
    • Hygiene for women
  8. Renovation of school (Boundary Wall & plaster, Fitting of Iron Gates)
Leadership: S. Shivraj Singh (Sarpanch), S. Gurmeet Singh
Beneficiaries: 665
No. of Houses: 133 – 100%
Completed year: 2007-08
Money Spent: Rs. 47.54 Lacs
FACILITIES PROVIDED
    1. Site Survey
    2. Detail Estimate
    3. Underground Sewerage System – 10685 rft.
    4. Water Supply (One part) – 6868 rft.
    5. Concreting of Streets – 64771 sqft.
    6. Septic Tank - 1 no.
    7. Sand Filter – 1 no.
    8. Control Room – 1 no
Beneficiaries: 456
No. of Houses: 76 – 100%
Completed year: 2009-10
Money Spent: Rs. 25.80 Lacs
FACILITIES PROVIDED
    1. Site Survey
    2. Detail Estimate
    3. Underground Sewerage System – 6730 rft.
    4. Water Supply (One part) – 6615 rft.
    5. Concreting of Streets – 29002 sqft.
Leadership: S. Anoop Singh (NRI), Smt.Satinder Kaur (Sarpanch), S. Harinder Singh
Beneficiaries: 900
No. of Houses: 180 – 100%
Completed year: 2009-10
Money Spent: Rs. 39.12 Lacs
FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 9938 rft.
  4. Water Supply (One part) – 136 rft.
  5. Concreting of Streets – 84361 sqft.
Leadership: S. Gurdial Singh Sangra, Mr. Krishan Kumar
Beneficiaries: 1200
No. of Houses: 236 – 100%
Completed year: 2009-10
Money Spent: Rs. 87.58 Lacs
FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 23385 rft.
  4. Water Supply – 16875 rft.
  5. Concreting of Streets – 127345 sqft.
  6. Septic Tank 2 nos.
  7. Solar Lights
Leadership: S. Manjit Singh, Sarpanch  
Beneficiaries: 1500
No. of Houses: 270 – 100%
Completed year: 2009-10
Money Spent: Rs. 46.27 Lacs
FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 14290 rft.
  4. Concreting of Streets – 88700 sqft.
  5. Septic Tank 2 nos.
  6. Collection Tank with Motor & Pump 1 no.
  7. Solar Lights
Leadership:   S. Jagmohan Singh,    Sh. Hari Singh
VILLAGE BRAHMPUR – District Ludhiana (Punjab) Beneficiaries: 1800 No. of Houses: 390 – 100% Completed year: 2005 Money Spent: Rs. 101.43 Lacs FACILITIES PROVIDED
  1. Site Survey
  2. Detail Estimate
  3. Underground Sewerage System – 17500 rft.
  4. Concreting of Streets – 168934 sqft.
  5. Water Supply with S. Pump (Some area-2400 ft.)
  6. Sewerage Treatment Plant
  7. Street Lights (Tube lights – 70 nos.)
  8. Training:-
    • Computer skill
    • Hygiene for women training
Leadership:  Mr.Anantpal Singh, Sh.Ram Narayan Singh